Minutes
Wednesday, January 9, 2008
| Members Present: | Staff Members Present: | |
Arrowood, Dan |
Bueno, Esther Cinclair, Richard Cook, Sharon Criswell, John Emery, John Farmer, Jim Gonzales, Lucinda Grigsby, Lindle Horak, Michael Jones, Jim |
King, Lenny Kozlowski, Gerald Marrero, Mike Moore, Tyler Smith, Benny Sykes, Art Thiehoff, Jack Washington, Michael Watts, Niki White, Bobbi Wyandon, Khaison Ross, Ann |
Welcome and Introductions
The Construction Team council convened on Wednesday, January 9, 2008 at 9:00a.m. Dr. Lindle Grigsby welcomed the members. Dr. Lindle Grigsby asked members to please sign the attendance sheet and to review the designated future team meeting dates.
Learning Studios
Dustin Moore with Rogers-O’Brien reported that the drilling piers should be complete by January 25, 2008. Work on the access to the electrical feeds and gas lines begins today. The restrooms inside the “L” building are all working properly, and the tile and dry wall work is expected to be completed this week and the additional stalls needed for the women’s restroom are on order.
Dan Arrowood reported there was no change to the bridge intersection. The original glass windows in the South end of the Library will again be opened as part of the bridge construction. Susan Hansen reported they received the building permit on December 14, 2007. Rogers Obrien has permits to begin vertical instruction on the Educational Building. The Project Management Team will meet with the City of Mesquite on Friday, 1/11/08 to continue the discussion of EFC building plans including new water line, retention ponds, sewer line, parking, etc. Susan reported they have one permit down and three remaining.
Parent Child Study Center Design
Rogers Obrien reported they have reviewed the schematic design. They are making cost saving proposals; however, there are no changes to the functional or structural project design. They anticipate scheduling “A User Group” meeting in the next few weeks. They are moving to the design development phase.
Johnnie Booth with Booth Architecture firm reported they will have construction plans ready for bid in June 2008.
Grove Campus
Darren James with KAI reported they have submitted required documentation to the City of Dallas for the Pleasant Grove Campus permits. Construction is planned to begin early in February 2008. The official address location is 802 South Buckner. The Pleasant Grove Campus
Ground Breaking ceremony is scheduled for Thursday, February 7, 2008 at 2:00p.m. Several city
officials and state representatives are expected to be in attendance.
Dr. Lindle Grigsby reported that the 95% drawings for the Pleasant Grove facility will returned today (1/9/08).
Workforce / Criminal Justice Facility
Halff Associates reported that the projections for the Workforce Development Center will be submitted on February 15, 2008. The initial drawings have been delivered and are available for viewing on the Eastfield College Campus in A-318. Susan Hansen asked if these drawings could be returned to her by January 18, 2008.
Technology “T” Building Expansion
Michael Johnson with Johnson McKibben commented on the following:
Eastfield College Courtyard Update
Functional Team Report
Jack Thiehoff reported on the following in reference to the Learning Space Building. He believes the overall concept can be used in the new buildings.
Open Discussion
Future Team Meeting Dates:
| February 6, 2008 March 5, 2008 April 9, 2008 May 7, 2008 June 4, 2008 July 9, 2008 |
August 6, 2008 September 3, 2008 October 8, 2008 November 5, 2008 December 3, 2008 |
Meeting adjourned 9:50a.m.