The Construction Team council convened on Wednesday, July 9, 2008 at 8:53a.m. Dr. Lindle Grigsby welcomed the members.
Learning Studios
Dustin Moore with Rogers-O’Brien reported the masonry work on the west side of building has begun. As the brick work is completed, going South and around the building, the stucco workers will begin following them. The roof trusses’ has begun and will match the existing buildings on campus. Interior framing on the first floor is basically complete and work has begun on the second floor. The Learning Studios building is scheduled to be complete by mid to late November 2008. The official opening ceremony will probably be held January 2009, no date has been selected.
Dan Arrowood reported they are working closely with Rogers-O’Brien.
What information is needed to move forward? Dustin Moore reported they have samples of “stained concrete” and will need input from Eastfield College Construction Team Members.
Center for Child and Parent Studies
Johnny Booth - Booth
Architects and Dan Arrowood with HKS reported they expect site plans to be
finalized by Friday, July 11, 2008. The architectural site plans have been approved by the city of
What information is needed to move forward? No additional information is needed at this time.
Pleasant Grove Campus
Brad Napier, with Adolfson & Peterson reported the foundation pier drilling will begin on Monday, July 14, 2008. Water and sewer lines are being installed. Grading for the drives and parking areas is almost complete so this area can be framed for concrete.
What information is needed to move forward? No additional information is needed at this time.
Workforce / Criminal Justice Facility
Halff Associates reported the
site plans are “nearly” complete. The first review period has been executed. The case manager with the city of
Susan Hansen reported they are
working with A&P on a tentative schedule to discuss the water and sewer trench
lines. Dave Littleton reiterated the need
of reminding the city of
Groundbreaking ceremony is scheduled for late July or early August 2008.
What information is needed to move forward? No additional information is needed at this time.
Michael Johnson with Johnson
McKibben Architectural firm reported 50% construction drawings
have been submitted and pricing received. 95% drawings are to be delivered by July 29, 2008. The site plan has been submitted to the
city of
What information is needed to move forward? No additional information is needed at this time.
Utility and Infrastructure Update
Dave Littleton with Halff Associates reported the revision to water line 3-plan will be submitted to the city of Mesquite today. Will begin work upon approval from the city.
Art Sykes reported the contractor will attempt to have the Oates drive entrance assessable by Monday, July 14, 2008. This is contingent upon building materials, i.e. concrete etc. being delivered on time. Additional scheduled dates:
What is needed to move forward? No additional information is needed at this time.
Perimeter Road
Representatives from Criado & Associates were not present at today’s meeting. No additional information was reported since last month’s meeting. A meeting is scheduled for next week with Craido and with Dave Littleton from Halff Associates on the La Prada entrance design.
Adaptive Remodel
Dr. Lindle Grigsby reported “work is continuing with the remodeling list from Eastfield. The architects and contractors are to complete their contract negotiations with the Bond Program Managers this next week and be ready for another walk through to see the nature of the changes since their last preview. Eastfield is still finalizing the list of remodeling projects.”
Parking Expansion
Dr. Lindle Grigsby reported
Furniture Team Visits
Jack Thiehoff reported all furniture have been selected for the Learning Studios building. Manufacturers have been notified of the pending orders so they can begin assembling the materials needed and staffing for the order that will be coming.
Dr. Lindle Grigsby and Susan Hansen will meet with Jack Thiehoff and Lucinda Gonzales immediately after today’s construction meeting to discuss the overall order.
Key Dates
(Source of information provided by Dr. Lindle Grigsby)
Open Discussion
Reminder:
Future Team Meeting Dates:
| August 6, 2008 September 3, 2008 October 8, 2008 |
November 5, 2008 December 3, 2008 |
Meeting adjourned 9:40a.m.